ARCHITECTURAL FEE GUIDELINES FOR INDIA


Construction Cost:   The cost of construction includes the cost of the construction of the building, site improvements, and all fixed and installed equipment. It does not include Furniture, Fixtures & Equipment (FF&E), testing, surveys, permits, land cost, studies, contingencies, or A&E fees.

PROJECT TYPES:
Group A  -  MORE THAN AVERAGE COMPLEXITY PROJECTS: New complex stand-alone facilities such as residential,commercial,special purpose classrooms, laboratory classrooms, libraries, auditoriums,  and food service facilities.
Group B - AVERAGE COMPLEXITY PROJECTS: Total facilities such as new elementary schools, middle schools, high schools, or large additions to existing facilities.
Group C - LESS THAN AVERAGE COMPLEXITY PROJECTS: New less complex stand-alone facilities such as warehouses, maintenance facilities, bus barns, offices, and storage facilities or any repetitive design use of a facility.
Group D - REPAIRS AND RENOVATIONS: Miscellaneous repairs and renovations, alterations to facilities, code corrective work or upgrades, system replacements, etc.

FEE GUIDELINE MULTIPLIER
Construction Cost:
Group A
Group B
Group C
Group D
Rs 0 to  Rs 10,00,000
8.8%
7.9%
7.2%
8.9%
Rs 10,00,000 to  Rs 40,00,000
7.8% - 8.8%
7.2% - 7.9%
6.6% - 7.2%
8.3% - 8.9%
Rs 40,00,000 to  Rs 1,00,00,000
7.2% - 7.8%
6.7% - 7.2%
6.2% - 6.6%
7.8% - 8.3%
Rs 1,00,00,000 to Rs 4,00,00,000
6.3% - 7.2%
6.0% - 6.7%
5.7% - 6.2%
7.2% - 7.8%
Rs 4,00,00,000 to Rs 10,00,00,000
6.0% - 6.3%
5.5% - 6.0%
5.3% - 5.7%
6.8% - 7.2%
Rs 10,00,00,000 to Rs 20,00,00,000
5.5% - 6.0%
5.5% - 6.0%
5.0% - 5.3%
5.7% - 6.8%
Rs 20,00,00,000 and above
5.5% - 6.0%
5.5% - 6.0%
4.3% to 5.0%
Up to 6.0%

FEE FORMULA:

Estimated Construction Cost _____________  x  Multiplier  ______ %  =  Fee